DA 29G Storm Drain Line A Replacement

Project Information

  • Project No.:  0330-6W9C14          

Project Description:  The work to be done generally consists of replacing a 48” culvert at two sites. Work includes removing trench plates, dewatering, trench shoring, placing 48” HDPE pipe, concrete slurry backfill and hot mix asphalt.

  • General Location: Antioch
  • Supervisory District:  5  
  • Location: Maritime Way, Antioch
  • Contractor: Kerex Engineering, Inc.
  • Project Engineer: Deborah Preciado, Phone: (925) 313-2267
  • Construction Start Date: August 17, 2020
  • Working Days: 20
  • Estimated Completion Date: September 18, 2020
  • Funding Source: Flood Control Funds